Estimating

Excavation job planner

Work out the loads, compare truck numbers and put a cost behind the job.

Example inputs. Replace quantities, cycle times and rates with your site figures.

Currency changes the label only. Enter all rates in the selected currency.

01 Quantity to excavate
02 Loading

Loading efficiency covers operating delays. Truck waiting is calculated separately.

03 Trucks & haul route

Enter usable material payload after allowances for the truck and its load limits. Set payload to 0 only for volume-only planning; the load weight will then be unchecked.

04 Rates & job costs

Machine rate excludes fuel and operator. Truck rate includes its driver and fuel. Do not enter the same cost twice.

05 Allowance & quote

Margin is calculated on the selling price. Tax is excluded.

Inputs have changed. Recalculate before using or saving this result.

Quote excluding taxUSD
USD 9,678.55

8.07 / bank m³ · 15% margin

Estimated job cost
8,226.77
Last load delivered
24.0 working h
Equivalent shifts
3.00
Loads
134

Material & loading

Bank quantity
1,200.0
Loose quantity
1,500.0
Usable load per truck
11.3
Bucket passes / full truck
11

Material payload limits each truck before its body is full.

Volume-only plan. Truck payload has not been checked.

Compare truck numbers

Lowest modeled cost: 4 trucks
TrucksDelivery hLoader waitingJob costUse

Finite job, including the partial final load. All selected trucks are on hire from job start until the last truck returns. Compare cost and duration together.

Cost breakdown

Excavator cost runs until loading finishes. Its fuel allowance includes waiting time at the entered average burn. Disposal is charged per loose unit.

Keep this estimate

Saved jobs stay in this browser. The share link contains numeric assumptions, not your job name or cost records.

What this plan includes

One excavator, identical trucks and one loading station. Each truck is filled within the entered body and material-payload limits. The final bucket and truck can carry a partial load. Loading efficiency, truck exchange, travel and unloading delays are separate inputs. Working shifts are equivalent hours, not a calendar schedule.

The cost covers only the rates and fixed allowances entered. Add excavation support, dewatering, testing, reinstatement, permits, disposal fees and other scope where applicable. Confirm actual payload limits and site conditions before pricing work.

Method and references

Bucket payload = bucket capacity × fill. Loose quantity = bank quantity × (1 + swell). A truck becomes available after loading, loaded travel, unloading and empty return. Loads are scheduled to the next available truck. Quote = cost including contingency ÷ (1 − margin).

See Volvo machine pairing and Caterpillar pass matching for production-planning context. This tool's finite-job scheduling and costing are Heavy Equipment Hub calculations.